The field guide
← Onboard templates

Onboard templates / v1

SEEMP, fuel data and CII review

MARPOL Annex VI; SEEMP, DCS, CII. At reporting cycle and operational change. Responsible: Shipowner energy manager.

MARPOL Annex VI; SEEMP, DCS, CII

Shipowner energy manager · At reporting cycle and operational change

Escalate unreliable data or missing required corrective planning.

01

Vessel and procedure

Vessel name and registry / IMO identifier, if applicable
Flag, vessel type, gross tonnage, use and voyage area
Actual event time, ship-local UTC offset and recorder
Approved procedure, version and applicable criteria
Responsible person / role
02

Before you begin

Determine tonnage, ship-type and reporting applicability.

Check approved SEEMP parts and verification evidence.

Reconcile fuel, distance and time data with source records.

03

What to record

Review attained CII and required improvement planning where applicable.

Assign operational measures and responsible owners.

Record submissions, verification and data corrections without claiming calculated compliance here.

04

Follow-up and review

Finding, immediate response, action owner and due date
Verification evidence, reviewer and next review trigger
Responsible person acknowledgement

Original operational starters, checked against the linked sources on 13 November 2026. Adapt with a competent maritime reviewer. They do not certify compliance or replace approved manuals, statutory surveys or accepted record books.