MARPOL Annex VI/14, 18. Before ECA entry and fuel changeover. Responsible: Chief engineer.
MARPOL Annex VI/14, 18
Chief engineer · Before ECA entry and fuel changeover
Escalate non-compliant fuel or failed approved equivalent arrangements.
01
Vessel and procedure
Vessel name and registry / IMO identifier, if applicable
Flag, vessel type, gross tonnage, use and voyage area
Actual event time, ship-local UTC offset and recorder
Approved procedure, version and applicable criteria
Responsible person / role
02
Before you begin
01
Review route and current emission control areas and implementation dates.
02
Check fuel sulphur specification, bunker notes and samples.
03
Review changeover procedure, timing and service-tank capacity.
03
What to record
04
Record actual changeover positions, times and quantities.
05
Verify exhaust gas cleaning system status where used.
06
Record unavailability reporting and corrective action without treating reporting as an exemption.
04
Follow-up and review
Finding, immediate response, action owner and due date
Verification evidence, reviewer and next review trigger
Responsible person acknowledgement
Original operational starters, checked against the linked sources on 13 November 2026. Adapt with a competent maritime reviewer. They do not certify compliance or replace approved manuals, statutory surveys or accepted record books.